East Nippon Expressway Company Limited. - Notice of Procurement (Goods & Services)(A1) ELECTRICITY TO USE IN KAN-ETSU TUNNEL MINAKAMI ELECTRIC POWER RECEIVING SUBSTATION, CONTRACT POWER 5,280KW THE ESTIMATED ELECTRICITY CONSUMPTION FOR THE DELIVERY PERIOD 15,960,000KWH ELECTRICITY TO USE IN MINAKAMI INTERCHANGE ELECTRIC POWER RECEIVING SUBSTATION, CONTRACT POWER 193KW THE E...

This procurement is covered by the WTO Agreement on Government Procurement, Japan-EU Economic Partnership Agreement or Japan-UK Comprehensive Economic Partnership Agreement.

Japanese

Publishing date Oct 13, 2017
Type of notice Notice of Procurement (Goods & Services)
Procurement entity East Nippon Expressway Company Limited. - Niigata
Classification
0026 Miscellaneous Articles
Summay of notice 5 Summary
(1) Official in charge ofdisbursement of the procuring
entity : Katsuhiko Sagae, DirectorGeneral of Niigata Regional Head
Office, East Nippon ExpresswayCompany Limited
(2) Classification of the products
to be procured : 26
(3) Nature and quantity of theproducts to be purchased :
(A1) Electricity to use inKan-etsu Tunnel minakami electric
power receiving substation,contract power : 5,280kW the
estimated electricity consumptionfor the delivery period :
15,960,000kWh
Electricity to use in MinakamiInterchange electric power
receiving substation, contractpower : 193kW the estimated
electricity consumption for thedelivery period : 977,000kWh
Electricity to use in KawakamiTunnel electric power receiving
substation, contract power : 54kWthe estimated electricity
consumption for the delivery period
: 289,000kWh
(A2) Electricity to use inKan-etsu Tunnel tsuchitaru electric
power receiving substation,contract power : 927kW the
estimated electricity consumptionfor the delivery period :
2,487,000kWh
Electricity to use inTsuchitaru Snowshed electric power
receiving substation, contractpower : 66kW the estimated
electricity consumption for thedelivery period : 208,000kWh
Electricity to use inShiozawa-Ishiuchi Interchange
electric power receivingsubstation, contract power : 219kW
the estimated electricityconsumption for the delivery period
: 600,000kWh
Electricity to use inMuikamachi Tunnel electric power
receiving substation, contractpower : 104kW the estimated
electricity consumption for thedelivery period : 344,000kWh
Electricity to use inMuikamachi Interchange electric
power receiving substation,contract power : 124kW the
estimated electricity consumptionfor the delivery period :
309,000kWh
Electricity to use in YamatoParking Area electric power
receiving substation, contractpower : 84kW the estimated
electricity consumption for thedelivery period : 241,000kWh
Electricity to use in KoideTunnel electric power receiving
substation, contract power : 152kWthe estimated electricity
consumption for the delivery period
: 427,000kWh
Electricity to use in KoideInterchange electric power
receiving substation, contractpower : 134kW the estimated
electricity consumption for thedelivery period : 389,000kWh
Electricity to use inShitagurayama Tunnel electric power
receiving substation, contractpower : 102kW the estimated
electricity consumption for thedelivery period : 329,000kWh
Electricity to use inHorinouchi Interchange electric
power receiving substation,contract power : 95kW the estimated
electricity consumption for thedelivery period : 381,000kWh
Electricity to use inEchigokawaguchi Tunnel electric
power receiving substation,contract power : 80kW the estimated
electricity consumption for thedelivery period : 234,000kWh
Electricity to use inEchigokawaguchi Interchange
electric power receivingsubstation, contract power : 74kW
the estimated electricityconsumption for the delivery period
: 307,000kWh
Electricity to use inEchigokawaguchi Service Area
electric power receivingsubstation,contract power : 379kW
the estimated electricityconsumption for the delivery period
: 1,894,000kWh
Electricity to use inYamamotoyama Tunnel electric power
receiving substation, contractpower : 277kW the estimated
electricity consumption for thedelivery period : 733,000kWh
(A3) Electricity to use inSanjo-Tsubame Interchange electric
power receiving substation,contract power : 110kW the
estimated electricity consumptionfor the delivery period :
741,000kWh
Electricity to use inMaki-Katahigashi
Interchange electric powerreceivingsubstation, contract power
: 65kW the estimated electricityconsumption for the delivery period
: 578,000kWh
Electricity to use in KurosakiParking Area upline electric power
receiving substation, contractpower : 178kW the estimated
electricity consumption for thedelivery period : 1,553,000kWh
Electricity to use in KurosakiParking Area downline electric
power receiving substation,contract power : 161kW the
estimated electricity consumptionfor the delivery period :
1,378,000kWh
Electricity to use inNiigata-Nishi-Daiichi Interchange
electric power receivingsubstation, contract power : 84kW
the estimated electricityconsumption for the delivery period
: 658,000kWh
Electricity to use in TsugawaInterchange electric power
receiving substation, contractpower : 82kW the estimated
electricity consumption for thedelivery period : 588,000kWh
Electricity to use in YakiyamaTunnel electric power receiving
substation, contract power : 238kWthe estimated electricity
consumption for the delivery period
: 953,000kWh
Electricity to use in MikawaInterchange electric power
receiving substation, contractpower : 58kW the estimated
electricity consumption for thedelivery period : 439,000kWh
Electricity to use in YoshizuTunnel electric power receiving
substation, contract power : 80kWthe estimated electricity
consumption for the delivery period
: 394,000kWh
Electricity to use in Nishiyama
Tunnel electric power receivingsubstation, contract power : 159kW
the estimated electricityconsumption for the delivery period
: 904,000kWh
Electricity to use in Aganogawa
Service Area electric powerreceiving substation, contract
power : 253kW the estimatedelectricity consumption for the
delivery period : 2,234,000kWh
Electricity to use in KomatsuTunnel electric power receiving
substation, contract power : 59kWthe estimated electricity
consumption for the delivery period
: 192,000kWh
Electricity to use in HoshusanTunnel electric power receiving
substation, contract power : 69kWthe estimated electricity
consumption for the delivery period
: 271,000kWh
Electricity to use in YasudaInterchange electric power
receiving substation, contractpower : 77kW the estimated
electricity consumption for thedelivery period : 537,000kWh
Electricity to use in NiitsuInterchange electric power
receiving substation, contractpower : 85kW the estimated
electricity consumption for thedelivery period : 552,000kWh
Electricity to use inNiigata-Chuo Interchange electric
power receiving substation,contract power : 131kW the
estimated electricity consumptionfor the delivery period :
1,035,000kWh
Electricity to use inNiigata-Kameda Interchange electric
power receiving substation,contract power : 345kW the
estimated electricity consumptionfor the delivery period :
3,513,000kWh
Electricity to use inNiigata-Higashi Smart Interchange
electric power receivingsubstation, contract power : 25kW
the estimated electricityconsumption for the delivery period
: 183,000kWh
Electricity to use in NiigataAirport Interchange electric power
receiving substation, contractpower : 69kW the estimated
electricity consumption for thedelivery period : 498,000kWh
Electricity to use inToyosaka-Niigatahigashiko
Interchange electric powerreceiving substation, contract
power : 76kW the estimatedelectricity consumption for the
delivery period : 469,000kWh
Electricity to use inSeiro-Shibata Interchange electric
power receiving substation,contract power : 91kW the estimated
electricity consumption for thedelivery period : 516,000kWh
Electricity to use in NakajoInterchange electric power
receiving substation, contractpower : 137kW the estimated
electricity consumption for thedelivery period : 964,000kWh
(A4) Electricity to use inKakizaki Tunnel electric power
receiving substation, contractpower : 98kW the estimated
electricity consumption for thedelivery period : 282,000kWh
Electricity to use in YoneyamaInterchange electric power
receiving substation, contractpower : 211kW the estimated
electricity consumption for thedelivery period : 1,030,000kWh
Electricity to use in KouchiTunnel electric power receiving
substation, contract power : 110kWthe estimated electricity
consumption for the delivery period
: 275,000kWh
Electricity to use inKashiwazaki Tunnel electric power
receiving substation, contractpower : 131kW the estimated
electricity consumption for thedelivery period : 370,000kWh
Electricity to use inKashiwazaki Interchange electric
power receiving
substation, contract power :95kW the estimated electricity
consumption for the delivery period
: 258,000kWh
Electricity to use in KariwaParking Area electric power
receiving substation, contractpower : 37kW the estimated
electricity consumption for thedelivery period : 112,000kWh
Electricity to use in Nishiyama
Interchange electric powerreceiving substation, contract
power : 84kW the estimatedelectricity consumption for the
delivery period : 222,000kWh
Electricity to use in ShinjizoTunnel electric power receiving
substation, contract power : 133kWthe estimated electricity
consumption for the delivery period
: 423,000kWh
Electricity to use inNakanoshima-Mitsuke Interchange
electric power receivingsubstation, contract power : 138kW
the estimated electricityconsumption for the delivery period
: 423,000kWh
Electricity to use in SakaeParking Area, Smart Interchange
electric power receivingsubstation, contract power : 206kW
the estimated electricityconsumption for the delivery period
: 784,000kWh
Electricity to use in OjiyaInterchange electric power
receiving substation, contractpower : 118kW the estimated
electricity consumption for thedelivery period : 245,000kWh
Electricity to use in YamayaParking Area electric power
receiving substation, contractpower : 49kW the estimated
electricity consumption for thedelivery period : 125,000kWh
Electricity to use in NagaokaJunction electric power receiving
substation, contract power : 141kWthe estimated electricity
consumption for the delivery period
: 166,000kWh
(A5) Electricity to use inOyashirazu Tunnel electric power
receiving substation, contractpower : 248kW the estimated
electricity consumption for thedelivery period : 1,017,000kWh
Electricity to use inOyashirazu Interchange electric
power receiving substation,contract power : 58kW the estimated
electricity consumption for thedelivery period : 244,000kWh
Electricity to use in Koshirazu
Tunnel electric power receivingsubstation, contract power : 379kW
the estimated electricityconsumption for the delivery period
: 2,014,000kWh
Electricity to use in IwakiTunnel electric power receiving
substation, contract power : 216kWthe estimated electricity
consumption for the delivery period
: 689,000kWh
Electricity to use in ItoigawaInterchange electric power
receiving substation, contractpower : 130kW the estimated
electricity consumption for thedelivery period : 427,000kWh
Electricity to use in HiraushiTunnel electric power receiving
substation, contract power : 98kWthe estimated electricity
consumption for the delivery period
: 454,000kWh
Electricity to use in KanayamaTunnel electric power receiving
substation, contract power : 113kWthe estimated electricity
consumption for the delivery period
: 428,000kWh
Electricity to use inTakanomine Tunnel electric power
receiving substation, contractpower : 208kW the estimated
electricity consumption for thedelivery period : 1,153,000kWh
Electricity to use in OnibushiTunnel electric power receiving
substation, contract power : 98kWthe estimated electricity
consumption for the delivery period
: 335,000kWh
Electricity to use in TaiheijiTunnel electric power receiving
substation, contract power : 104kWthe estimated electricity
consumption for the delivery period
: 382,000kWh
Electricity to use in NouInterchange electric power
receiving substation, contractpower : 67kW the estimated
electricity consumption for thedelivery period : 226,000kWh
Electricity to use in SannouTunnel electric power receiving
substation, contract power : 560kWthe estimated electricity
consumption for the delivery period
: 1,479,000kWh
Electricity to use in TokuaiTunnel electric power receiving
substation, contract power : 890kWthe estimated electricity
consumption for the delivery period
: 1,173,000kWh
Electricity to use in NadachiTunnel electric power receiving
substation, contract power : 175kWthe estimated electricity
consumption for the delivery period
: 522,000kWh
Electricity to use inNadachi-Tanihama Interchange
electric power receivingsubstation, contract power : 262kW
the estimated electricityconsumption for the delivery period
: 1,119,000kWh
Electricity to use in YakushiTunnel electric power receiving
substation, contract power : 215kWthe estimated electricity
consumption for the delivery period
: 841,000kWh
Electricity to use inKasugayama Tunnel electric power
receiving substation, contractpower : 230kW the estimated
electricity consumption for thedelivery period : 854,000kWh
Electricity to use in JoetsuInterchange electric power
receiving substation, contractpower : 231kW the estimated
electricity consumption for thedelivery period : 754,000kWh
Electricity to use in OgataParking Area electric power
receiving substation, contractpower : 46kW the estimated
electricity consumption for thedelivery period : 203,000kWh
Electricity to use inKakizaki-Seppyoubunshitsu electric
power receiving substation,contract power : 21kW the estimated
electricity consumption for thedelivery period : 30,000kWh
Electricity to use in KakizakiInterchange electric power
receiving substation, contractpower : 73kW the estimated
electricity consumption for thedelivery period : 231,000kWh
Electricity to use inMyokokougen Interchange electric
power receiving substation,contract power : 80kW the estimated
electricity consumption for thedelivery period : 294,000kWh
Electricity to use in NakagoInterchange electric power
receiving substation, contractpower : 83kW the estimated
electricity consumption for thedelivery period : 288,000kWh
Electricity to use in TenjindoTunnel electric power receiving
substation, contract power : 700kWthe estimated electricity
consumption for the delivery period
: 729,000kWh
Electricity to use inKannondaira Tunnel electric power
receiving substation, contractpower : 130kW the estimated
electricity consumption for thedelivery period : 451,000kWh
Electricity to use in Kanayasan
Tunnel electric power receivingsubstation, contract power : 75kW
the estimated electricityconsumption for the delivery period
: 200,000kWh
Electricity to use inJoetsu-Takada Interchange electric
power receiving substation,contract power : 66kW the estimated
electricity consumption for thedelivery period : 247,000kWh
(A6) Electricity to use in Tomari
Tunnel electric power receivingsubstation, contract power : 81kW
the estimated electricityconsumption for the delivery period
: 502,000kWh
Electricity to use in Shiroyama
Tunnel electric power receivingsubstation, contract power : 205kW
the estimated electricityconsumption for the delivery period
: 1,641,000kWh
Electricity to use inEtchusakai Parking Area electric
power receiving substation,contract power : 37kW the estimated
electricity consumption for thedelivery period : 302,000kWh
Electricity to use in SakaiTunnel electric power receiving
substation contract power : 226kWthe estimated electricity
consumption for the delivery period
: 1,543,000kWh
(4) Delivery period : from 1April, 2018 through 31 March, 2020
((3)(A1), (A3), (A6)) and from 1April, 2018 through 31 March, 2019
((3)(A2), (A4), (A5))
(5) Delivery places : As shown inthe tender documentation
(6) Qualification forparticipating in the tendering
procedures : Suppliers eligible for
participating in the open tenderare those who shall :
(A1) not come under Article 6 ofthe East Nippon Expressway
Company's regulation concerning the
contract procedures
(A2) have a qualification andpast record, which apply to one of
the following 1) or 2).
1) Being a general electricenterprise in accordance with
Article 3 of the ElectricityUtilities Industry Law.
2) Being a specified-scaleelectric enterprise in accordance
with Article 2-2 of the aforesaidLaw and who have the electricity
supply results which it suppliesconsumers excepting the person who
request participating in thetendering procedure, and term of a
contract completed.
3) [(A2)2) needs onlypertinence] Being the person who
can confirm the electricity supplyresults by copying of the contract
which it supplies consumersexcepting the person who request
participating in the tenderingprocedure, and term of a contract
completed.
(7) Time-limit for tender : 4 : 00
PM, 4 December, 2017
(8) Contact point for the notice :
Kazumichi Hirai, Deputy Manager of
procurement & contract Section,Technology and procurement
Department, Niigata Regional HeadOffice, East Nippon Expressway
Company Limited, 1-1, Tenjin,Chuo-ku, Niigata city, Niigata
950-0917, Japan. TEL 025-241-5116