East Nippon Expressway Company Limited. - Notice of Procurement (Goods & Services)Electricity to use in Tohoku Expressway, Ajara PA electric receiving place, contract power : 31kW the estimated electricity consumption for the delivery period : 350,000kWh

This procurement is covered by the WTO Agreement on Government Procurement, Japan-EU Economic Partnership Agreement or Japan-UK Comprehensive Economic Partnership Agreement.

Japanese

Publishing date Oct 11, 2021
Type of notice Notice of Procurement (Goods & Services)
Procurement entity East Nippon Expressway Company Limited. - Miyagi
Classification
0026 Miscellaneous Articles
Summay of notice ⑴ Official in charge of the contract of the procuring entity : YAGI Shigeki, Director General of Tohoku Regional Head Office, East Nippon Expressway Company Limited
⑵ Classification of the products to be procured : 26
⑶ Nature and quantity of the products to be purchased :
Electricity to use in Tohoku Expressway, Ajara PA electric receiving place, contract power : 31kW the estimated electricity consumption for the delivery period : 350,000kWh
Electricity to use in Tohoku Expressway, Owani Tunnel electric receiving place, contract power : 43kW the estimated electricity consumption for the delivery period : 380,000kWh
Electricity to use in Tohoku Expressway, Owanihirosaki IC electric receiving place, contract power : 72kW the estimated electricity consumption for the delivery period : 900,000kWh
Electricity to use in Tohoku Expressway, Tsugaru SA electric receiving place, contract power : 106kW the estimated electricity consumption for the delivery period : 1,600,000kWh
Electricity to use in Tohoku Expressway, Kuroishi IC electric receiving place, contract power : 57kW the estimated electricity consumption for the delivery period : 760,000kWh
Electricity to use in Tohoku Expressway, Takadate PA electric receiving place, contract power : 24kW the estimated electricity consumption for the delivery period : 310,000kWh
Electricity to use in Tohoku Expressway, Namioka IC electric receiving place, contract power : 62kW the estimated electricity consumption for the delivery period : 820,000kWh
Electricity to use in Tohoku Expressway, Aomori TB electric receiving place, contract power : 197kW the estimated electricity consumption for the delivery period : 2,400,000kWh
Electricity to use in Aomori Expressway, Iwatari Tunnel electric receiving place, contract power : 83kW the estimated electricity consumption for the delivery period : 700,000kWh
Electricity to use in Aomori Expressway, Aomorichuo IC electric receiving place, contract power : 134kW the estimated electricity consumption for the delivery period : 1,500,000kWh
Electricity to use in Aomori Expressway, Inayama Tunnel electric receiving place, contract power : 60kW the estimated electricity consumption for the delivery period : 500,000kWh
Electricity to use in Tohoku Expressway, Magata Tunnel electric receiving place, contract power : 104kW the estimated electricity consumption for the delivery period : 940,000kWh
Electricity to use in Tohoku Expressway, Nashiki Tunnel electric receiving place, contract power : 94kW the estimated electricity consumption for the delivery period : 770,000kWh
Electricity to use in Tohoku Expressway, Tayama Tunnel electric receiving place, contract power : 63kW the estimated electricity consumption for the delivery period : 740,000kWh
Electricity to use in Tohoku Expressway, Sahinai Tunnel electric receiving place, contract power : 175kW the estimated electricity consumption for the delivery period : 1,300,000kWh
Electricity to use in Tohoku Expressway, Ishidoshi Tunnel electric receiving place, contract power : 117kW the estimated electricity consumption for the delivery period : 1,100,000kWh
Electricity to use in Tohoku Expressway, Sasanowatari Tunnel electric receiving place, contract power : 102kW the estimated electricity consumption for the delivery period : 860,000kWh
Electricity to use in Tohoku Expressway, Gonomiya Tunnel electric receiving place, contract power : 41kW the estimated electricity consumption for the delivery period : 310,000kWh
Electricity to use in Tohoku Expressway, Kazunohachimantai IC electric receiving place, contract power : 55kW the estimated electricity consumption for the delivery period : 810,000kWh
Electricity to use in Tohoku Expressway, Hanawa SA electric receiving place, contract power : 47kW the estimated electricity consumption for the delivery period : 680,000kWh
Electricity to use in Tohoku Expressway, Towada IC electric receiving place, contract power : 169kW the estimated electricity consumption for the delivery period : 2,000,000kWh
Electricity to use in Tohoku Expressway, Kamedayama Tunnel electric receiving place, contract power : 120kW the estimated electricity consumption for the delivery period : 1,200,000kWh
Electricity to use in Tohoku Expressway, Kosaka IC electric receiving place, contract power : 54kW the estimated electricity consumption for the delivery period : 700,000kWh
Electricity to use in Tohoku Expressway, Kosaka JCT electric receiving place, contract power : 81kW the estimated electricity consumption for the delivery period : 1,100,000kWh
Electricity to use in Tohoku Expressway, Sakanashi Tunnel electric receiving place, contract power : 520kW the estimated electricity consumption for the delivery period : 3,700,000kWh
Electricity to use in Tohoku Expressway, Ikarigaseki Tunnel electric receiving place, contract power : 75kW the estimated electricity consumption for the delivery period : 500,000kWh
Electricity to use in Tohoku Expressway, Ikarigaseki IC electric receiving place, contract power : 85kW the estimated electricity consumption for the delivery period : 1,100,000kWh
Electricity to use in Tohoku Expressway, Hanamaki IC electric receiving place, contract power : 78kW the estimated electricity consumption for the delivery period : 1,000,000kWh
Electricity to use in Tohoku Expressway, Shiwa SA electric receiving place, contract power : 232kW the estimated electricity consumption for the delivery period : 3,300,000kWh
Electricity to use in Tohoku Expressway, Shiwa IC electric receiving place, contract power : 60kW the estimated electricity consumption for the delivery period : 830,000kWh
Electricity to use in Tohoku Expressway, Yahaba PA electric receiving place, contract power : 28kW the estimated electricity consumption for the delivery period : 330,000kWh
Electricity to use in Tohoku Expressway, Moriokaminami IC electric receiving place, contract power : 236kW the estimated electricity consumption for the delivery period : 2,900,000kWh
Electricity to use in Tohoku Expressway, Morioka IC electric receiving place, contract power : 79kW the estimated electricity consumption for the delivery period : 1,100,000kWh
Electricity to use in Tohoku Expressway, Takizawa PA electric receiving place, contract power : 31kW the estimated electricity consumption for the delivery period : 460,000kWh
Electricity to use in Tohoku Expressway, Takizawa IC electric receiving place, contract power : 79kW the estimated electricity consumption for the delivery period : 1,000,000kWh
Electricity to use in Tohoku Expressway, Nishine IC electric receiving place, contract power : 98kW the estimated electricity consumption for the delivery period : 1,100,000kWh
Electricity to use in Tohoku Expressway, Iwatesan SA electric receiving place, contract power : 251kW the estimated electricity consumption for the delivery period : 4,000,000kWh
Electricity to use in Tohoku Expressway, Matsuohachimantai IC electric receiving place, contract power : 65kW the estimated electricity consumption for the delivery period : 870,000kWh
Electricity to use in Tohoku Expressway, Ryugamori Tunnel electric receiving place, contract power : 162kW the estimated electricity consumption for the delivery period : 2,300,000kWh
Electricity to use in Tohoku Expressway, Hata PA electric receiving place, contract power : 28kW the estimated electricity consumption for the delivery period : 360,000kWh
Electricity to use in Tohoku Expressway, Hodosaka Tunnel electric receiving place, contract power : 101kW the estimated electricity consumption for the delivery period : 850,000kWh
Electricity to use in Hachinohe Expressway, Ashiro JCT electric receiving place, contract power : 32kW the estimated electricity consumption for the delivery period : 340,000kWh
Electricity to use in Tohoku Expressway, Ashiro IC electric receiving place, contract power : 118kW the estimated electricity consumption for the delivery period : 1,200,000kWh
Electricity to use in Hachinohe Expressway, Joboji IC electric receiving place, contract power : 67kW the estimated electricity consumption for the delivery period : 840,000kWh
Electricity to use in Tohoku Expressway, Takizawachuo SIC electric receiving place, contract power : 83kW the estimated electricity consumption for the delivery period : 570,000kWh
Electricity to use in Tohoku Expressway, Ichinoseki IC electric receiving place, contract power : 76kW the estimated electricity consumption for the delivery period : 970,000kWh
Electricity to use in Tohoku Expressway, Ichinoseki Tunnel electric receiving place, contract power : 116kW the estimated electricity consumption for the delivery period : 1,200,000kWh
Electricity to use in Tohoku Expressway, Hiraizumi Tunnel electric receiving place, contract power : 126kW the estimated electricity consumption for the delivery period : 1,400,000kWh
Electricity to use in Tohoku Expressway, Hiraizumimaesawa IC electric receiving place, contract power : 71kW the estimated electricity consumption for the delivery period : 880,000kWh
Electricity to use in Tohoku Expressway, Maesawa SA electric receiving place, contract power : 252kW the estimated electricity consumption for the delivery period : 3,700,000kWh
Electricity to use in Tohoku Expressway, Mizusawa IC electric receiving place, contract power : 80kW the estimated electricity consumption for the delivery period : 970,000kWh
Electricity to use in Tohoku Expressway, Kitakamikanegasaki IC electric receiving place, contract power : 76kW the estimated electricity consumption for the delivery period : 1,100,000kWh
Electricity to use in Tohoku Expressway, Kitakamiezuriko IC electric receiving place, contract power : 169kW the estimated electricity consumption for the delivery period : 2,100,000kWh
Electricity to use in Tohoku Expressway, Hanamaki PA electric receiving place, contract power : 27kW the estimated electricity consumption for the delivery period : 390,000kWh
Electricity to use in Tohoku Expressway, Hanamakiminami IC electric receiving place, contract power : 58kW the estimated electricity consumption for the delivery period : 720,000kWh
Electricity to use in Akita Expressway, Kitakami JCT electric receiving place, contract power : 34kW the estimated electricity consumption for the delivery period : 290,000kWh
Electricity to use in Akita Expressway, Kitakaminishi IC electric receiving place, contract power : 76kW the estimated electricity consumption for the delivery period : 930,000kWh
Electricity to use in Akita Expressway, Yamaguchi Tunnel electric receiving place, contract power : 56kW the estimated electricity consumption for the delivery period : 340,000kWh
Electricity to use in Akita Expressway, Wagasennin Tunnel electric receiving place, contract power : 589kW the estimated electricity consumption for the delivery period : 2,100,000kWh
Electricity to use in Akita Expressway, Togeyama Tunnel electric receiving place, contract power : 231kW the estimated electricity consumption for the delivery period : 980,000kWh
Electricity to use in Akita Expressway, Kinshuko SA electric receiving place, contract power : 76kW the estimated electricity consumption for the delivery period : 1,100,000kWh
Electricity to use in Akita Expressway, Yuda Tunnel electric receiving place, contract power : 173kW the estimated electricity consumption for the delivery period : 1,800,000kWh
Electricity to use in Akita Expressway, Kawajiri Tunnel electric receiving place, contract power : 57kW the estimated electricity consumption for the delivery period : 430,000kWh
Electricity to use in Akita Expressway, Yuda IC electric receiving place, contract power : 74kW the estimated electricity consumption for the delivery period : 900,000kWh
Electricity to use in Kamaishi Expressway, Hanamaki JCT electric receiving place, contract power : 25kW the estimated electricity consumption for the delivery period : 270,000kWh
Electricity to use in Kamaishi Expressway, HanamakiAirport IC electric receiving place, contract power : 53kW the estimated electricity consumption for the delivery period : 640,000kWh
Electricity to use in Kamaishi Expressway, HanamakiAirport TB electric receiving place, contract power : 46kW the estimated electricity consumption for the delivery period : 420,000kWh
Electricity to use in Kamaishi Expressway, Towa IC electric receiving place, contract power : 22kW the estimated electricity consumption for the delivery period : 190,000kWh
Electricity to use in Tohoku Expressway, Shiroishi IC electric receiving place, contract power : 59kW the estimated electricity consumption for the delivery period : 800,000kWh
Electricity to use in Tohoku Expressway, Murata IC electric receiving place, contract power : 44kW the estimated electricity consumption for the delivery period : 600,000kWh
Electricity to use in Tohoku Expressway, Sugo PA electric receiving place, contract power : 395kW the estimated electricity consumption for the delivery period : 5,700,000kWh
Electricity to use in Tohoku Expressway, Sendaiminami IC electric receiving place, contract power : 76kW the estimated electricity consumption for the delivery period : 1,100,000kWh
Electricity to use in Tohoku Expressway, Sendaimiyagi IC electric receiving place, contract power : 590kW the estimated electricity consumption for the delivery period : 8,500,000kWh
Electricity to use in Tohoku Expressway, Izumi TB electric receiving place, contract power : 41kW the estimated electricity consumption for the delivery period : 610,000kWh
Electricity to use in Tohoku Expressway, Izumi IC electric receiving place, contract power : 97kW the estimated electricity consumption for the delivery period : 1,200,000kWh
Electricity to use in Tohoku Expressway, Tsurusu PA electric receiving place, contract power : 169kW the estimated electricity consumption for the delivery period : 2,700,000kWh
Electricity to use in Tohoku Expressway, Taiwa IC electric receiving place, contract power : 73kW the estimated electricity consumption for the delivery period : 930,000kWh
Electricity to use in Tohoku Expressway, Ohira IC electric receiving place, contract power : 38kW the estimated electricity consumption for the delivery period : 530,000kWh
Electricity to use in Tohoku Expressway, Sanbongi PA electric receiving place, contract power : 55kW the estimated electricity consumption for the delivery period : 640,000kWh
Electricity to use in Tohoku Expressway, Furukawa IC electric receiving place, contract power : 163kW the estimated electricity consumption for the delivery period : 2,000,000kWh
Electricity to use in Tohoku Expressway, Chojahara SA electric receiving place, contract power : 430kW the estimated electricity consumption for the delivery period : 6,600,000kWh
Electricity to use in Tohoku Expressway, Tsukidate IC electric receiving place, contract power : 63kW the estimated electricity consumption for the delivery period : 840,000kWh
Electricity to use in Tohoku Expressway, Wakayanagikannari IC electric receiving place, contract powe : 62kW the estimated electricity consumption for the delivery period : 700,000kWh
Electricity to use in Tohoku Expressway, Kannari PA electric receiving place, contract power : 28kW the estimated electricity consumption for the delivery period : 400,000kWh
Electricity to use in Yamagata Expressway, Murata JCT electric receiving place, contract power : 20kW the estimated electricity consumption for the delivery period : 250,000kWh
Electricity to use in Yamagata Expressway, Hoshinojo Tunnel electric receiving place, contract power : 61kW the estimated electricity consumption for the delivery period : 450,000kWh
Electricity to use in Yamagata Expressway, Miyagikawasaki IC electric receiving place, contract power : 74kW the estimated electricity consumption for the delivery period : 880,000kWh
Electricity to use in Joban Expressway, Yamamoto IC electric receiving place, contract power : 44kW the estimated electricity consumption for the delivery period : 450,000kWh
Electricity to use in Sendaitobu Road, Watari IC electric receiving place, contract power : 40kW the estimated electricity consumption for the delivery period : 570,000kWh
Electricity to use in Sendaitobu Road, Iwanuma IC electric receiving place, contract power : 55kW the estimated electricity consumption for the delivery period : 780,000kWh
Electricity to use in Sendaitobu Road, SendaiAirport IC electric receiving place, contract power : 64kW the estimated electricity consumption for the delivery period : 870,000kWh
Electricity to use in Sendaitobu Road, Natori IC electric receiving place, contract power : 54kW the estimated electricity consumption for the delivery period : 780,000kWh
Electricity to use in Sendaitobu Road, Sendaiwakabayashi JCT electric receiving place, contract power : 14kW the estimated electricity consumption for the delivery period : 190,000kWh
Electricity to use in Sendaitobu Road, Sendaihigashi IC electric receiving place, contract power : 194kW the estimated electricity consumption for the delivery period : 2,500,000kWh
Electricity to use in Sendaitobu Road, Sendaiko IC electric receiving place, contract power : 46kW the estimated electricity consumption for the delivery period : 620,000kWh
Electricity to use in Sanriku Expressway, Sendaikokita IC electric receiving place, contract power : 63kW the estimated electricity consumption for the delivery period : 810,000kWh
Electricity to use in Sanriku Expressway, Tagajo IC electric receiving place, contract power : 46kW the estimated electricity consumption for the delivery period : 540,000kWh
Electricity to use in Sanriku Expressway, Rifushiogama IC electric receiving place, contract power : 41kW the estimated electricity consumption for the delivery period : 610,000kWh
Electricity to use in Sendaihokubu Road, Rifushirakashidai IC electric receiving place, contract power : 52kW the estimated electricity consumption for the delivery period : 660,000kWh
Electricity to use in Sendaihokubu Road, Tomiya JCT electric receiving place, contract power : 21kW the estimated electricity consumption for the delivery period : 300,000kWh
Electricity to use in Sendaihokubu Road, Tomiya IC electric receiving place, contract power : 57kW the estimated electricity consumption for the delivery period : 670,000kWh
Electricity to use in Sendainanbu Road, Imaizumi IC electric receiving place, contract power : 40kW the estimated electricity consumption for the delivery period : 600,000kWh
Electricity to use in Sendainanbu Road, Nagamachi IC electric receiving place, contract power : 93kW the estimated electricity consumption for the delivery period : 1,400,000kWh
Electricity to use in Sendainanbu Road, Yamada IC electric receiving place, contract power : 55kW the estimated electricity consumption for the delivery period : 770,000kWh
Electricity to use in Tohoku Expressway, Motomiya IC electric receiving place, contract power : 55kW the estimated electricity consumption for the delivery period : 760,000kWh
Electricity to use in Tohoku Expressway, Adatara SA electric receiving place, contract power : 429kW the estimated electricity consumption for the delivery period : 5,800,000kWh
Electricity to use in Tohoku Expressway, Nihonmatsu IC electric receiving place, contract power : 63kW the estimated electricity consumption for the delivery period : 770,000kWh
Electricity to use in Tohoku Expressway, Fukushimamatsukawa PA electric receiving place, contract power : 60kW the estimated electricity consumption for the delivery period : 890,000kWh
Electricity to use in Tohoku Expressway, Fukushima Tunnel electric receiving place, contract power : 175kW the estimated electricity consumption for the delivery period : 1,700,000kWh
Electricity to use in Tohoku Expressway, Fukushimanishi IC electric receiving place, contract power : 89kW the estimated electricity consumption for the delivery period : 1,200,000kWh
Electricity to use in Tohoku Expressway, Azuma PA electric receiving place, contract power : 52kW the estimated electricity consumption for the delivery period : 790,000kWh
Electricity to use in Tohoku Expressway, Fukushima JCT electric receiving place, contract power : 57kW the estimated electricity consumption for the delivery period : 610,000kWh
Electricity to use in Tohoku Expressway, Fukushimaiizaka IC electric receiving place, contract power : 143kW the estimated electricity consumption for the delivery period : 2,000,000kWh
Electricity to use in Tohoku Expressway, Kunimi IC electric receiving place, contract power : 55kW the estimated electricity consumption for the delivery period : 680,000kWh
Electricity to use in Tohoku Expressway, Kunimi SA electric receiving place, contract power : 136kW the estimated electricity consumption for the delivery period : 1,900,000kWh
Electricity to use in Tohoku Expressway, Shirakawa IC electric receiving place, contract power : 81kW the estimated electricity consumption for the delivery period : 910,000kWh
Electricity to use in Tohoku Expressway, Abukuma PA electric receiving place, contract power : 40kW the estimated electricity consumption for the delivery period : 590,000kWh
Electricity to use in Tohoku Expressway, Yabuki IC electric receiving place, contract power : 48kW the estimated electricity consumption for the delivery period : 670,000kWh
Electricity to use in Tohoku Expressway, Kagamiishi PA electric receiving place, contract power : 51kW the estimated electricity consumption for the delivery period : 770,000kWh
Electricity to use in Tohoku Expressway, Sukagawa IC electric receiving place, contract power : 71kW the estimated electricity consumption for the delivery period : 760,000kWh
Electricity to use in Tohoku Expressway, Asaka PA electric receiving place, contract power : 182kW the estimated electricity consumption for the delivery period : 2,700,000kWh
Electricity to use in Tohoku Expressway, Koriyamaminami IC electric receiving place, contract power : 49kW the estimated electricity consumption for the delivery period : 640,000kWh
Electricity to use in Tohoku Expressway, Koriyama IC electric receiving place, contract power : 190kW the estimated electricity consumption for the delivery period : 2,400,000kWh
Electricity to use in Banetsu Expressway, Shinkazakoshi Tunnel electric receiving place, contract power : 239kW the estimated electricity consumption for the delivery period : 620,000kWh
Electricity to use in Banetsu Expressway, Abukumakogen SA electric receiving place, contract power : 232kW the estimated electricity consumption for the delivery period : 3,200,000kWh
Electricity to use in Banetsu Expressway, Funehikimiharu IC electric receiving place, contract power : 149kW the estimated electricity consumption for the delivery period : 770,000kWh
Electricity to use in Banetsu Expressway, Koriyamahigashi IC electric receiving place, contract power : 108kW the estimated electricity consumption for the delivery period : 960,000kWh
Electricity to use in Banetsu Expressway, Koriyama JCT electric receiving place, contract power : 53kW the estimated electricity consumption for the delivery period : 640,000kWh
Electricity to use in Banetsu Expressway, Gohyakugawa PA electric receiving place, contract power : 40kW the estimated electricity consumption for the delivery period : 540,000kWh
Electricity to use in Banetsu Expressway, Tamura SIC electric receiving place, contract power : 44kW the estimated electricity consumption for the delivery period : 330,000kWh
Electricity to use in Banetsu Expressway, Watado Tunnel electric receiving place, contract power : 181kW the estimated electricity consumption for the delivery period : 1,500,000kWh
Electricity to use in Banetsu Expressway, Ono IC electric receiving place, contract power : 148kW the estimated electricity consumption for the delivery period : 920,000kWh
Electricity to use in Hachinohe Expressway, Ninohe PA electric receiving place, contract power : 34kW the estimated electricity consumption for the delivery period : 430,000kWh
Electricity to use in Hachinohe Expressway, Ichinohe Tunnel electric receiving place, contract power : 68kW the estimated electricity consumption for the delivery period : 510,000kWh
Electricity to use in Hachinohe Expressway, Ichinohe IC electric receiving place, contract power : 74kW the estimated electricity consumption for the delivery period : 920,000kWh
Electricity to use in Hachinohe Expressway, Oritsume Tunnel electric receiving place, contract power : 144kW the estimated electricity consumption for the delivery period : 1,700,000kWh
Electricity to use in Hachinohe Expressway, Kunohe IC electric receiving place, contract power : 64kW the estimated electricity consumption for the delivery period : 820,000kWh
Electricity to use in Hachinohe Expressway, Oritsume SA electric receiving place, contract power : 39kW the estimated electricity consumption for the delivery period : 550,000kWh
Electricity to use in Hachinohe Expressway, Karumai IC electric receiving place, contract power : 69kW the estimated electricity consumption for the delivery period : 790,000kWh
Electricity to use in Hachinohe Expressway, Nango IC electric receiving place, contract power : 65kW the estimated electricity consumption for the delivery period : 770,000kWh
Electricity to use in Hachinohe Expressway, Hachinohe JCT electric receiving place, contract power : 76kW the estimated electricity consumption for the delivery period : 940,000kWh
Electricity to use in Hachinohe Expressway, Hachinohe TB electric receiving place, contract power : 152kW the estimated electricity consumption for the delivery period : 1,800,000kWh
Electricity to use in Hachinohe Expressway, Hachinohekita IC electric receiving place, contract power : 178kW the estimated electricity consumption for the delivery period : 1,100,000kWh
Electricity to use in Momoishi Road, Shimodamomoishi IC electric receiving place, contract power : 47kW the estimated electricity consumption for the delivery period : 610,000kWh
Electricity to use in Hachinohe Road, Hachinohenishi IC electric receiving place, contract power : 93kW the estimated electricity consumption for the delivery period : 880,000kWh
Electricity to use in Akita Expressway, Kurosawa Tunnel electric receiving place, contract power : 54kW the estimated electricity consumption for the delivery period : 440,000kWh
Electricity to use in Akita Expressway, Sannai Tunnel electric receiving place, contract power : 249kW the estimated electricity consumption for the delivery period : 1,300,000kWh
Electricity to use in Akita Expressway, Tsuchibuchi Tunnel electric receiving place, contract power : 91kW the estimated electricity consumption for the delivery period : 410,000kWh
Electricity to use in Akita Expressway, Osawa-Yokote Tunnel electric receiving place, contract power : 126kW the estimated electricity consumption for the delivery period : 1,000,000kWh
Electricity to use in Akita Expressway, Yokote IC electric receiving place, contract power : 57kW the estimated electricity consumption for the delivery period : 760,000kWh
Electricity to use in Akita Expressway, Yokote JCT electric receiving place, contract power : 109kW the estimated electricity consumption for the delivery period : 1,400,000kWh
Electricity to use in Akita Expressway, Omagari IC electric receiving place, contract power : 63kW the estimated electricity consumption for the delivery period : 790,000kWh
Electricity to use in Akita Expressway, Nishisenboku SA electric receiving place, contract power : 127kW the estimated electricity consumption for the delivery period : 1,800,000kWh
Electricity to use in Akita Expressway, Kyowa Tunnel electric receiving place, contract power : 78kW the estimated electricity consumption for the delivery period : 670,000kWh
Electricity to use in Yuzawayokote Road, Yuzawa IC electric receiving place, contract power : 12kW the estimated electricity consumption for the delivery period : 180,000kWh
Electricity to use in Yuzawayokote Road, Jumonji IC electric receiving place, contract power : 128kW the estimated electricity consumption for the delivery period : 1,300,000kWh
Electricity to use in Yuzawayokote Road, Yokotekita SIC electric receiving place, contract power : 196kW the estimated electricity consumption for the delivery period : 860,000kWh
Electricity to use in Akita Expressway, Kyowa IC electric receiving place, contract power : 58kW the estimated electricity consumption for the delivery period : 750,000kWh
Electricity to use in Nihonkaitohoku Expressway, Kawabe JCT electric receiving place, contract power : 32kW the estimated electricity consumption for the delivery period : 360,000kWh
Electricity to use in Akita Expressway, Akitaminami IC electric receiving place, contract power : 168kW the estimated electricity consumption for the delivery period : 2,100,000kWh
Electricity to use in Akita Expressway, Akitachuo IC electric receiving place, contract power : 52kW the estimated electricity consumption for the delivery period : 670,000kWh
Electricity to use in Akita Expressway, Akitakita IC electric receiving place, contract power : 71kW the estimated electricity consumption for the delivery period : 770,000kWh
Electricity to use in Akita Expressway, Showaogahanto IC electric receiving place, contract power : 55kW the estimated electricity consumption for the delivery period : 770,000kWh
Electricity to use in Akita Expressway, Gojomehatirogata IC electric receiving place, contract power : 69kW the estimated electricity consumption for the delivery period : 730,000kWh
Electricity to use in Akita Expressway, Ichino Tunnel electric receiving place, contract power : 43kW the estimated electricity consumption for the delivery period : 320,000kWh
Electricity to use in Akita Expressway, Kotookamoritake IC electric receiving place, contract power : 93kW the estimated electricity consumption for the delivery period : 1,100,000kWh
Electricity to use in Nihonkaitohoku Expressway, AkitaAirport IC electric receiving place, contract power : 52kW the estimated electricity consumption for the delivery period : 610,000kWh
Electricity to use in Nihonkaitohoku Expressway, AkitaAirport TB electric receiving place, contract power : 43kW the estimated electricity consumption for the delivery period : 430,000kWh
Electricity to use in Nihonkaitohoku Expressway, Michikawa Tunnel electric receiving place, contract power : 69kW the estimated electricity consumption for the delivery period : 510,000kWh
Electricity to use in Nihonkaitohoku Expressway, Iwaki IC electric receiving place, contract power : 22kW the estimated electricity consumption for the delivery period : 180,000kWh
Electricity to use in Yamagata Expressway, Sasaya IC electric receiving place, contract power : 81kW the estimated electricity consumption for the delivery period : 980,000kWh
Electricity to use in Yamagata Expressway, Sasaya Tunnel electric receiving place, contract power : 359kW the estimated electricity consumption for the delivery period : 3,500,000kWh
Electricity to use in Yamagata Expressway, Sekizawa IC electric receiving place, contract power : 44kW the estimated electricity consumption for the delivery period : 630,000kWh
Electricity to use in Yamagata Expressway, Niyama Tunnel electric receiving place, contract power : 153kW the estimated electricity consumption for the delivery period : 1,200,000kWh
Electricity to use in Yamagata Expressway, Shirahige Tunnel electric receiving place, contract power : 113kW the estimated electricity consumption for the delivery period : 1,100,000kWh
Electricity to use in Yamagata Expressway, Yamagatazao IC electric receiving place, contract power : 126kW the estimated electricity consumption for the delivery period : 1,400,000kWh
Electricity to use in Yamagata Expressway, Sakazukiyama Tunnel electric receiving place, contract power : 196kW the estimated electricity consumption for the delivery period : 1,500,000kWh
Electricity to use in Yamagata Expressway, Yanbe Tunnel electric receiving place, contract power : 87kW the estimated electricity consumption for the delivery period : 520,000kWh
Electricity to use in Yamagata Expressway, Aono Tunnel electric receiving place, contract power : 183kW the estimated electricity consumption for the delivery period : 1,100,000kWh
Electricity to use in Yamagata Expressway, Yamagatakita IC electric receiving place, contract power : 135kW the estimated electricity consumption for the delivery period : 2,000,000kWh
Electricity to use in Yamagata Expressway, Sagae IC electric receiving place, contract power : 60kW the estimated electricity consumption for the delivery period : 720,000kWh
Electricity to use in Yamagata Expressway, Hiranoyama Tunnel electric receiving place, contract power : 75kW the estimated electricity consumption for the delivery period : 610,000kWh
Electricity to use in Yamagata Expressway, Nishikawa IC electric receiving place, contract power : 80kW the estimated electricity consumption for the delivery period : 930,000kWh
Electricity to use in Yamagata Expressway, Tsunatorihigashi Tunnel electric receiving place, contract power : 66kW the estimated electricity consumption for the delivery period : 610,000kWh
Electricity to use in Yamagata Expressway, Fumyozan Tunnel electric receiving place, contract power : 127kW the estimated electricity consumption for the delivery period : 970,000kWh
Electricity to use in Yamagata Expressway, Tsukiyamazawa Tunnel electric receiving place, contract power : 52kW the estimated electricity consumption for the delivery period : 660,000kWh
Electricity to use in Yamagata Expressway, Gassan IC electric receiving place, contract power : 27kW the estimated electricity consumption for the delivery period : 220,000kWh
Electricity to use in Tohokuchuo Expressway, Yamagatakaminoyama IC electric receiving place, contract power : 54kW the estimated electricity consumption for the delivery period : 630,000kWh
Electricity to use in Tohokuchuo Expressway, Yamagatachuo IC electric receiving place, contract power : 59kW the estimated electricity consumption for the delivery period : 650,000kWh
Electricity to use in Tohokuchuo Expressway, Yamagata JCT electric receiving place, contract power : 48kW the estimated electricity consumption for the delivery period : 470,000kWh
Electricity to use in Tohokuchuo Expressway, Tendo IC electric receiving place, contract power : 51kW the estimated electricity consumption for the delivery period : 580,000kWh
Electricity to use in Tohokuchuo Expressway, Higashine IC electric receiving place, contract power : 19kW the estimated electricity consumption for the delivery period : 160,000kWh
Electricity to use in Tohokuchuo Expressway, Yonezawakita IC electric receiving place, contract power : 22kW the estimated electricity consumption for the delivery period : 220,000kWh
Electricity to use inTohokuchuo Expressway, Yonezawakita TB electric receiving place, contract power : 232kW the estimated electricity consumption for the delivery period : 1,200,000kWh
Electricity to use in Tohokuchuo Expressway, Tendo TB electric receiving place, contract power : 175kW the estimated electricity consumption for the delivery period : 850,000kWh
Electricity to use in Tohokuchuo Expressway, Yamagatazao Tunnel electric receiving place, contract power : 53kW the estimated electricity consumption for the delivery period : 510,000kWh
Electricity to use in Tohokuchuo Expressway, Sankichiyama Tunnel electric receiving place, contract power : 102kW the estimated electricity consumption for the delivery period : 970,000kWh
Electricity to use inTohokuchuo Expressway, Kaminoyamaonsen IC electric receiving place, contract power : 226kW the estimated electricity consumption for the delivery period : 1,100,000kWh
Electricity to use in Tohokuchuo Expressway, Nishigo Tunnel electric receiving place, contract power : 167kW the estimated electricity consumption for the delivery period : 980,000kWh
Electricity to use in Tohokuchuo Expressway, Ohora Tunnel electric receiving place, contract power : 40kW the estimated electricity consumption for the delivery period : 390,000kWh
Electricity to use in Tohokuchuo Expressway, Akayu Tunnel electric receiving place, contract power : 244kW the estimated electricity consumption for the delivery period : 1,600,000kWh
Electricity to use inTohokuchuo Expressway, Nanyotakahata IC electric receiving place, contract power : 269kW the estimated electricity consumption for the delivery period : 1,900,000kWh
Electricity to use in Yamagata Expressway, Tamugimata Tunnel electric receiving place, contract power : 140kW the estimated electricity consumption for the delivery period : 1,500,000kWh
Electricity to use in Yamagata Expressway, Mikuriya Tunnel electric receiving place, contract power : 127kW the estimated electricity consumption for the delivery period : 1,000,000kWh
Electricity to use in Yamagata Expressway, Tateiwa Tunnel electric receiving place, contract power : 43kW the estimated electricity consumption for the delivery period : 300,000kWh
Electricity to use in Yamagata Expressway, Tsuruoka IC electric receiving place, contract power : 197kW the estimated electricity consumption for the delivery period : 2,300,000kWh
Electricity to use in Nihonkaitohoku Expressway, Tsuruoka JCTTB electric receiving place, contract power : 57kW the estimated electricity consumption for the delivery period : 650,000kWh
Electricity to use in Nihonkaitohoku Expressway, Sakata IC electric receiving place, contract power : 94kW the estimated electricity consumption for the delivery period : 1,100,000kWh
Electricity to use in Nihonkaitohoku Expressway, Sakataminato Tollgate electric receiving place, contract power : 64kW the estimated electricity consumption for the delivery period : 630,000kWh
Electricity to use in Joban Expressway, Iwakinakoso IC electric receiving place, contract power : 50kW the estimated electricity consumption for the delivery period : 670,000kWh
Electricity to use in Joban Expressway, Iwakiyumoto IC electric receiving place, contract power : 55kW the estimated electricity consumption for the delivery period : 730,000kWh
Electricity to use in Joban Expressway, Iwakichuo IC electric receiving place, contract power : 147kW the estimated electricity consumption for the delivery period : 2,000,000kWh
Electricity to use in Joban Expressway, Yoshima Tunnel electric receiving place, contract power : 85kW the estimated electricity consumption for the delivery period : 750,000kWh
Electricity to use in Joban Expressway, Iwakiyotsukura IC electric receiving place, contract power : 26kW the estimated electricity consumption for the delivery period : 380,000kWh
Electricity to use in Joban Expressway, Ohisa Tunnel electric receiving place, contract power : 71kW the estimated electricity consumption for the delivery period : 370,000kWh
Electricity to use in Joban Expressway, Hirono IC electric receiving place, contract power : 32kW the estimated electricity consumption for the delivery period : 410,000kWh
Electricity to use in Joban Expressway, Jobantomioka IC electric receiving place, contract power : 34kW the estimated electricity consumption for the delivery period : 480,000kWh
Electricity to use in Joban Expressway, Namie IC electric receiving place, contract power : 40kW the estimated electricity consumption for the delivery period : 560,000kWh
Electricity to use in Joban Expressway, Haramachi Tunnel electric receiving place, contract power : 40kW the estimated electricity consumption for the delivery period : 320,000kWh
Electricity to use in Joban Expressway, Minamisoma IC electric receiving place, contract power : 66kW the estimated electricity consumption for the delivery period : 800,000kWh
Electricity to use in Joban Expressway, Minamisomakashima SA electric receiving place, contract power : 62kW the estimated electricity consumption for the delivery period : 720,000kWh
Electricity to use in Joban Expressway, Soma IC electric receiving place, contract power : 38kW the estimated electricity consumption for the delivery period : 800,000kWh
Electricity to use in Joban Expressway, Shinchi IC electric receiving place, contract power : 53kW the estimated electricity consumption for the delivery period : 650,000kWh
Electricity to use in Banetsu Expressway, Iwaki JCT electric receiving place, contract power : 27kW the estimated electricity consumption for the delivery period : 360,000kWh
Electricity to use in Banetsu Expressway, Godo Tunnel electric receiving place, contract power : 74kW the estimated electricity consumption for the delivery period : 410,000kWh
Electricity to use in Banetsu Expressway, Iwakimiwa IC electric receiving place, contract power : 44kW the estimated electricity consumption for the delivery period : 640,000kWh
Electricity to use in Joban Expressway, Okuma IC electric receiving place, contract power : 29kW the estimated electricity consumption for the delivery period : 460,000kWh
Electricity to use in Joban Expressway, Jobanfutaba IC electric receiving place, contract power : 29kW the estimated electricity consumption for the delivery period : 500,000kWh
Electricity to use in Banetsu Expressway, Bandaiatami IC electric receiving place, contract power : 56kW the estimated electricity consumption for the delivery period : 710,000kWh
Electricity to use in Banetsu Expressway, Takadama Tunnel electric receiving place, contract power : 300kW the estimated electricity consumption for the delivery period : 3,100,000kWh
Electricity to use in Banetsu Expressway, Kurateyama Tunnel electric receiving place, contract power : 146kW the estimated electricity consumption for the delivery period : 1,300,000kWh
Electricity to use in Banetsu Expressway, Sekito Tunnel electric receiving place, contract power : 109kW the estimated electricity consumption for the delivery period : 1,200,000kWh
Electricity to use in Banetsu Expressway, Inawashirobandaikogen IC electric receiving place, contract power : 80kW the estimated electricity consumption for the delivery period : 1,100,000kWh
Electricity to use in Banetsu Expressway, Bandaisan SA electric receiving place, contract power : 222kW the estimated electricity consumption for the delivery period : 3,300,000kWh
Electricity to use in Banetsu Expressway, Bandaikawahigashi IC electric receiving place, contract power : 73kW the estimated electricity consumption for the delivery period : 930,000kWh
Electricity to use in Banetsu Expressway, Aizuwakamatsu IC electric receiving place, contract power : 196kW the estimated electricity consumption for the delivery period : 2,400,000kWh
Electricity to use in Banetsu Expressway, Niitsuru PA electric receiving place, contract power : 100kW the estimated electricity consumption for the delivery period : 910,000kWh
Electricity to use in Banetsu Expressway, Nanaori Tunnel electric receiving place, contract power : 226kW the estimated electricity consumption for the delivery period : 1,400,000kWh
Electricity to use in Banetsu Expressway, Aizubange IC electric receiving place, contract power : 56kW the estimated electricity consumption for the delivery period : 700,000kWh
Electricity to use in Banetsu Expressway, Tabanematsu Tunnel electric receiving place, contract power : 80kW the estimated electricity consumption for the delivery period : 930,000kWh
Electricity to use in Banetsu Expressway, Toyasan Tunnel electric receiving place, contract power : 277kW the estimated electricity consumption for the delivery period : 2,300,000kWh
Electricity to use in Banetsu Expressway, Nishiaizu IC electric receiving place, contract power : 90kW the estimated electricity consumption for the delivery period : 1,100,000kWh
Electricity to use in Banetsu Expressway, Nagasaka Tunnel electric receiving place, contract power : 192kW the estimated electricity consumption for the delivery period : 890,000kWh
Electricity to use in Banetsu Expressway, Ryugatake Tunnel electric receiving place, contract power : 386kW the estimated electricity consumption for the delivery period : 2,400,000kWh
Electricity to use in Banetsu Expressway, Kuromoriyama Tunnel electric receiving place, contract power : 365kW the estimated electricity consumption for the delivery period : 2,100,000kWh
Electricity to use in Banetsu Expressway, Koide Tunnel electric receiving place, contract power : 265kW the estimated electricity consumption for the delivery period : 1,100,000kWh
⑷ Delivery period : from 1 April, 2022 through 31 March, 2025
⑸ Delivery place : As shown in the specifications
⑹ Time-Limit for the submission of application forms and relevant documents for the qualification : 16 : 00 30 November, 2021
⑺ Time-Limit for the submission of tender : 16 : 00 30, November, 2021
⑻ Contact point for tender documentation : KIYONO Nobuki, Deputy Manager of Procurement & Contract Section, Technol-ogy & Procurement Department, Tohoku Regional Head Office, East Nippon Expressway Company Limited 1-1-1, Tsutsujigaoka, miyagino-ku, Sendai City, Miyagi Prefecture, 983-8477 Japan
TEL 022-395-7574
E-mail : ki-r-tohoku@e-nexco.co.jp