Electricity that will be used by Tokushima Bunka no Mori Park Estimated Amount of Electric Power: 4,693,000 kWh

Procuring Entity Tokushima Pref.
Category 0026 Miscellaneous Articles
Publication Date

Feb 17, 2017

Deadline Mar 29, 2017
Summary Summary
1 Description and quantity of the products being purchased:
Electricity that will be used by Tokushima Bunka no Mori Park
Estimated Amount of Electric Power: 4,693,000 kWh
2 Period for the Submission of Bids
Hand delivered submissions: March 30th, 2017 by 1:30 p.m.
Submissions by mail: Must be delivered between March 24th, 2017 and
March 29th, 2017.
3 For further information, please send all enquiries to the following
address:
Tokushima 21st Century Cultural Information Center
Mukouterayama Hachiman-cho, Tokushima City, 770-8070 Japan
Tel: 088-668-1369

ID 931d1b563e13856f