Tottori PrefectureConstruction works of the Kure Tunnel on Route 181

Japanese

Publishing date Jul 23, 2024
Procurement entity Tottori Prefecture(Tottori)
Classification
0041 Construction Services
Summary of notice Summary
(1) Subject matter of the contract:
Construction works of the Kure Tunnel on Route 181
Construction method: NATM (New Austrian Tunnelling Method)
Construction length: 2,609.0 m
Tunnel part: 2,609.0 m, width 6.5 (8.0) m
(2) Deadline for the submission of documents for the qualification confirmation: 5:00 PM, 5
August, 2024
(3) Date and time for submission of tenders: 4:00 PM, 20 September, 2024
(Deadline for the submission of tenders by registered mail: 4:00 PM, 20 September, 2024)
(4) Please contact: Prefectural land General Affairs Division, Tottori Prefectural Government 1
-220 Higashi-machi Tottori-shi 680-8570 Japan, TEL 0857-26-7347