Tokyo-toPhase III construction work for the sand settling basin building for the 2nd Asakusa System of the Mikawashima Water Reclamation Center

Japanese

Publishing date Jun 12, 2023
Procurement entity Tokyo-to(Tokyo)
Classification
0041 Construction Services
Summary of notice Summary
(1) Nature and Quantity
Phase III construction work for the sand settling basin building for the 2nd Asakusa System of the Mikawashima Water
Reclamation Center
(2) Location of Work or Location of Implementation
25-1 Arakawa 8-chome, Arakawa-ku, Tokyo (in the Mikawashima Water Reclamation Center)
(3) Work Period or Implementation Period
For 920 days from the day following the day of conclusion of the contract
(4) Language and currency used in the contracting procedure
The language and currency used in the contracting procedure shall be Japanese and Japanese currency.
(5) Time Limit of Tender by electronic bidding
5:00 p.m. on August 23 (Wednesday), 2023
(6) Inquiry Section regarding Notice of Tender
Contracting Section, Accounting and Contracting Division, Bureau of Sewerage
E-mail: S4000013@section.metro.tokyo.jp