Hiroshima PrefectureElectric power to be consumed at Hiroshima Prefectural Senogawa Water Purification Plant and 5 other facilities as per the attached paper Estimated annual consumption of electric power of each facility noted in the attached paper

Japanese

Publishing date Jul 01, 2020
Procurement entity Hiroshima Prefecture(Hiroshima)
Classification
0026 Miscellaneous Articles
Summary of notice Summary
(1) Nature and quantity of the products to be purchased: Electric power to be consumed
at Hiroshima Prefectural Senogawa Water Purification Plant and 5 other facilities
as per the attached paper
Estimated annual consumption of electric power of each facility noted in the
attached paper
(2) Fulfillment period: From 1 November 2020 through 31 October 2023 (A long-term
continuing contract based on the regulations, Article 234-3 of the Local Government
Act)
(3) Fulfillment place: As per the attached paper
(4) Time-limit for the submission of application forms and relevant documents for the
qualification: 5:00 p.m. 15 June 2020
(5) Time-limit for tender: 10:00 a.m. 21 August 2020
(6) Contact point for the notice: General Affairs Division, Hiroshima Prefectural
Hiroshima Water Service Office
2970 Hataka-cho, Aki-ku, Hiroshima-shi 736-0089 Japan
TEL 082-827-1123